77范文网 - 专业文章范例文档资料分享平台

电力需求与定价(15)

来源:网络收集 时间:2021-01-20 下载这篇文档 手机版
说明:文章内容仅供预览,部分内容可能不全,需要完整文档或者需要复制内容,请下载word后使用。下载word有问题请添加微信号:或QQ: 处理(尽可能给您提供完整文档),感谢您的支持与谅解。点击这里给我发消息

peak period consumers. Therefore, if the capacity costs of

base load generating units are included in the calculations, it

is very important to net out potential fuel savings due to

displacement of less efficient plant by these new base load

units (see Appendix for details). Even intuitively, it would not

be sensible to incorrectly charge peak consumers the highcapacity

costs of expensive base load units (e.g., nuclear), thus

encouraging them, for example to install their own captive gas

turbine plant.

Next, the LRMC of transmission and distribution (T&D) are

calculated. Generally, all T&D investment costs (except customer

costs-discussed later) are allocated to incremental capacity,

because the designs of these facilities are determined

principally by the peak kilowatt that they carry rather than

the kwh. However, particularly at the distribution level, the

size of a given feeder may depend on local peak demand which

may not occur within the system peak period and this could

complicate the problem of allocating distribution capacity

costs among the various rating periods [3]. The concept of

structuring by voltage level may be introduced at this stage.

Consider three supply voltage categories: high, medium, and

low (HV, MV, LV). Since consumers at each voltage level are

charged only upstream costs, capacity costs at each voltage

level must be identified.

The simplest approach is to use the average incremental cost

(AIC) method to estimate the LRMC of T&D. Suppose that in

year i, AMWi, and Ii are the increase in demand served (relative

to the previous year), and the investment cost respectively.

Then, the AIC of capacity is given by:

AIC = 1 i=o

where r is the discount rate (e.g., the opportunity cost of capital),

T is the planning horizon (e.g., 10 years), and L is the

average time delay between the investment and commissioning

dates for new facilities. We note that in the AIC method the

actual additional increments of demand are considered as they

occur, rather than the hypothetical fixed demand increment

AD used (more rigorously) in calculating generation LRMC.

However, because there is no problem of plant mix with T&D

investments, AIC and the hypothetical increment method will

yield similar results, while AIC is also usually much easier to

calculate using readily available planning data. An alternative

百度搜索“77cn”或“免费范文网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,免费范文网,提供经典小说教育文库电力需求与定价(15)在线全文阅读。

电力需求与定价(15).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印 下载失败或者文档不完整,请联系客服人员解决!
本文链接:https://www.77cn.com.cn/wenku/jiaoyu/1179829.html(转载请注明文章来源)
Copyright © 2008-2022 免费范文网 版权所有
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ: 邮箱:tiandhx2@hotmail.com
苏ICP备16052595号-18
× 注册会员免费下载(下载后可以自由复制和排版)
注册会员下载
全站内容免费自由复制
注册会员下载
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: