毕 业 设 计 论 文
题 目 矿井提升设备的选型和设计 __ (院)系 大同煤炭职业技术学院
专业 机电一体化 (矿山机电) 班级 学号 学生姓名 王飞
导师姓名 王富军 完成日期 2011年5月1日
目 录
第1章 矿井提升设备···································································································· 2
一、提升方式················································································································ 2
二、主提升设备选型计算···························································································· 2
三、开采煤时主提升能力计算···················································································· 13
四、副提升设备选型计算···························································································· 16
五、开采煤时副井提升能力校核················································································ 28
六、煤井下主要运输设备选型···················································································· 31
结束语······························································································································· 34
参考文献··························································································································· 36
附录 A 采区供电系统图 附录 B 设备布置图
第一章 矿井提升设备
一、提升方式
矿井七2煤与二1煤采用分期开拓开采的方式,初期开采七2煤,后期经技术改造后开采二1煤。七2煤井设计生产能力为0.30Mt/a,采用立井开拓,二个提升井筒,其中主井井深277m,担负七2煤矿井提煤任务;副井井深277m,担负七2煤矿井辅助提升任务;二1煤井设计生产能力为0.45Mt/a,采用立井开拓,利用七2煤井二个提升井筒延深至二1煤的开采水平,在七2煤井开采结束后进行二1煤的开采,二1煤主井井深577m,担负二1煤矿井提煤任务;副井井深577m,担负二1煤矿井辅助提升任务。
二、主提升设备选型计算 (一)设计依据 初期开采七2煤时 1、生产能力:0.30Mt/a
2、工作制度:年工作日330d,每天净提升时间16h。 3、井深:H=277m
4、提升方式:双箕斗提升,采用定重装载。 后期开采二1煤时 1、生产能力:0.45Mt/a
2、工作制度:年工作日330d,每天净提升时间16h。 3、井深:H=577m
4、提升方式:双箕斗提升,采用定重装载。 (二)提升容器选择 该矿井初期开采七
2
煤时井深277m,后期开采二
1
煤时井深
577m,根据《煤炭工业矿井设计规范》规定,为避免提升系统的重复改扩建,同时考虑到矿井后期开采二1煤时井筒深度增加,所以初期开采七2煤和后期开采二1煤时主、副井提升设备统一按开采最终水平选择计算。计算过程以后期开采二1煤的提升设备选型计算为准。
1、确定经济提升速度 V=(0.3-0.5)×577=7.2-12.01m/s
取:Vm=8m/s,α1=1.0m/s2 2、计算一次提升循环时间: Tx =+
185778+10+8=98.1s
3、根据矿井年产量和一次提升循环时间即可求出一次提升量。 Qj=
450000?1.2?1.2?98.13600?330?16=3.3t
据此提升容器选择JDS-4/55×4Y型标准多绳箕斗(钢丝绳罐道),箕斗自重QZ=6500kg(含连接装置),载重量Q=4000kg,提升钢丝绳4根,平衡尾绳2根,钢丝绳间距300mm。
(三)钢丝绳选择 1、绳端荷重
Qd=QZ+Q=6500+4000=10500kg 2、钢丝绳悬垂长度
Hc=H-HZ+Hh+HX+Hg+Hr+0.75RT+e=577-30+11.008+12+6.5+10.9+0.75×0.925+5=593.1m
式中:Hg ---过卷高度 Hg=6.5m
Hh ---尾绳环高度 Hh=Hg+0.5+2S=6.5+0.5+2×2.004=11.008m
Hr ---容器高度 Hr=10.9m RT---天轮半径
e---上下天轮垂直距离 e=5m S---提升容器中心距 HX ---卸载高度 HX=12m 3、首绳单位长度重量计算
Qd10500?Hc)110?Bm110?1677PK′ =
n(=
4?(?593.1)=1.29kg/m
式中:δB—钢丝绳计算抗拉强度,取1670MPa
m—钢丝绳安全系数,取7
根据以上计算,首绳选用22ZAB-6V×30+FC-1670-307型钢丝绳左右捻各两根。其技术参数如下:钢丝绳直径dk=22mm,钢丝破断拉力总和Qq=307200N,钢丝绳单位长度质量为Pk=1.96kg/m。
4、尾绳单位长度重量计算 qk′=?Pk=×1.96=3.92kg/m
2n式中:n—首绳钢丝绳根数 n=4
n′—尾绳钢丝绳根数 n′=2
根据以上计算,尾绳选用88×15NAT-P8×4×7-1360型扁钢丝绳2根,单重q=3.82kg/m。
(四)提升机选择
n4