附录4输电线路工程施工安全管理及风险控制方案编制模板
封面样式
隋尔、隋阎35KV线路迁移改造 工程
施工安全管理及风险
控制方案
编制单位:
编制时间: 年 月 日
1
批 准(分管领导) 技术审核(技术部门) 安全审核(安全部门) 编 写(项目总工) 年 月 日
年 月 日
年 月 日年 月 日2
本方案模板系依照输变电工程施工安全管理及风险控制方案编制标准编写的,用于指导、示范各单位具体方案的编制。模板中【编制要点】是对各章节的内容提出的重点要求,是必须包含和遵守的要求。【示例】是依照某个工程实例编制的,供方案编制时参考,编写者可根据各自工程特点进行深化、细化、适应性调整。
3
目 录
1.概述 ························· 1
1.1 编制目的 ··············································································· 1 1.2 编制依据 ··············································································· 1 1.3 工程概况 ··············································································· 3 2.安全目标 ······················· 4
2.1 安全管理目标 ······································································· 4 2.2 环境保护及水土保持目标 ···················································· 4 2.3 文明施工目标 ······································································· 5 3.安全管理机构及职责 ·················· 5
3.1 保证机构 ··············································································· 5 3.2 监督机构 ··············································································· 7 3.3 安全职责 ··············································································· 8 4.施工安全管理措施 ·················· 13
4.1 作业人员基本条件 ····························································· 13 4.2 安全管理制度和台帐 ························································· 14 4.3 施工安全方案管理 ····························································· 17 4.4 安全生产费用管理 ····························································· 19 4.5 作业人员行为管理 ····························································· 20 4.6 施工安全风险 ····································································· 21 4.7 应急管理措施 ····································································· 23 5.施工安全风险管理 ·················· 24
5.1施工安全风险管理措施 ························································ 24 5.2施工重大风险及预控措施 ····················································· 26 5.2.1 施工准备阶段 ··································································· 26 5.2.2 基础施工阶段 ··································································· 29
4
5.2.3杆塔组立阶段 ···································································· 34 5.2.4 架线施工阶段 ··································································· 39 5.2.5 特殊环境 ··········································································· 50 6.安全文明施工管理 ·················· 54
6.1 施工准备阶段 ······································································· 54 6.2 基础施工阶段 ······································································· 60 6.3杆塔组立阶段 ········································································ 62 6.4 架线施工阶段 ······································································· 64 7.环境保护 ······················ 66
7.1 防止大气污染 ····································································· 66 7.2 防止水土污染 ····································································· 67 7.3 防止噪声污染 ····································································· 67 8.分包安全管理 ···················· 68 9.安全检查及隐患排查 ················· 70 10.信息管理 ····················· 71 11.安全管理评价···················· 72 附件1 “悬浮内(外)抱杆分解组立铁塔”安全风险预控措施 73 附件2 “跨越××线高速铁路53m高度钢管跨越架搭设、拆除”安全风险预控措施 ···················· 80 附表1 施工安全措施补助费使用计划表 ·········· 85 附表2 文明施工措施费使用计划 ············· 87 附表3:应急物资清单 ·················· 90