陕西建工安装集团有限公司 SCEGC Installation Group Co., Ltd
the ladder, platform and other accessories installed. Finally, the whole crane installed in place. 3.4动设备施工要点
3.4. Key points of construction of motivate equipment
3.4.1动设备安装程序 3.4.1. Installation Procedures
检查、清点
单体试车 联轴器复位电机与泵对中 联轴器拆卸电机试运转 配管及试压吹扫 设备二次灌浆 预留地脚螺栓孔灌浆 设备二次找正、找平 机组各部分间隙测量,精找正 随机文件
基础质量检查、验收
基础处理 垫铁放置
设备就位及初找正、找平
The equipment site inspection---base inspection and acceptance–iron pad adjust—equipment positioning and alignment--- grouting of anchor bolts--- second alignment--- equipment second alignment and survey----second grouting ---piping pressure test clean---Shaft coupling disassembly motor test run--Coupling reset motor and pump pair—Unit testing.
3.4.2泵安装方法及技术要求
3.4.2. Installation method and technical requirement of pump (1)施工准备
(1) Construction preparation
熟悉图纸,编写施工技术措施,对施工人员进行技术交底。做好施工机具、量具、手段用料及消耗材料的准备工作。
To be Familiar with the drawings, preparation of construction technical measures, the construction personnel technical clarification. Do a good job in the construction machines and
16
陕西建工安装集团有限公司 SCEGC Installation Group Co., Ltd
tools, measuring tools, tools and materials and material consumption of the preparatory work.
(2)设备到货验收
(2).Site acceptance of equipment
泵到货后,由物资供应部门组织业主、承包方、监理及其他有关人员共同进行开箱检验。泵的开箱检查应检查以下内容:
After the arrival of the pump, the material supply department calls for owners, the contractor, supervision and other relevant personnel together to open package for inspection. Pump check out of the box should check for the following:
a、泵的出厂合格证明书
a. Manufacturer’s certificate for pumps
b、制造厂提供的有关重要零件和部件的制造、装配等质量检验证书及泵的试运转记录;
b. Manufacturing, assembly and other quality inspection certificates and pump test run records of important parts and components;
c、按设备技术文件的规定清点泵的零件、部件和备件,检查有无缺件、损坏和锈蚀等现象,并检查管口保护和堵盖是否完好;
c. As specified in the technical documentation of the equipment inventory pump parts, components and spare parts, check whether the lack of parts, damage and corrosion phenomenon, and check the pipe to protect and blocking cover is in good condition;
d、核对泵的主要安装尺寸并应与工程设计相核对;
D.Check the main installation dimensions of the pump and should check with the engineering design;
e、核对主要零件、密封件以及垫片的品种和规格;
E.Check the main parts, seals and gaskets of the varieties and specifications; f、检查规范要求试压部件的试压记录。
F.Check the specification requirements to test the pressure parts of the test record. (3)基础的验收 (3). Basis of acceptance
泵基础使用前必须办理交接手续,基础移交时必须同时提供施工质量合格证书及中心、标高、外形尺寸实测记录等资料。
17
陕西建工安装集团有限公司 SCEGC Installation Group Co., Ltd
Prior to the use of the pump base, the transfer procedures must be handled on the basis of transferring quality certificate and the center, elevation, shape and size of the recorded data.
对基础进行外观及尺寸检查,应满足下列要求:
On the basis of the appearance and size of the inspection, should meet the following requirements:
a、不得有裂纹、蜂窝、空洞、露筋等缺陷;
A.There must be no crack, honeycomb, void, dew and other defects; b、基础中心线、标高、沉降观测点等标记齐全、清晰;
B.Basic center line, elevation, settlement observation points, such as complete, clear; c、具体实测值应符合下表的要求;
C.Actual measured value should be in accordance with the requirements of the following table;
泵基础允许偏差/ Pump base deviation allowable
项次 SN 1 position (vertical, horizontal axis) 基础不同平面的标高 2 Base elevation of different planes 基础上平面的外形尺寸 Based on the plane of the shape ±20 凸台上平面外形尺寸 3 SizePlane shape dimension of convex platform +20 凹穴尺寸Cavity size 基础平面水平度/ base plane leveling 4 每米/ per meter 全长/ total length 5 垂直度/ vertical 18
偏差名称 Deviation Items 基础的坐标位置(纵、横轴线)Base coordinate 允许偏差Deviation allowable (mm) ±20 +0 / -20 -20 5 10 陕西建工安装集团有限公司 SCEGC Installation Group Co., Ltd
项次 SN 每米/ per meter 全长 偏差名称 Deviation Items 允许偏差Deviation allowable (mm) 5 10 ±10 +20 10 预留地脚螺栓孔:holes for anchor bolts 中心位置/ center position 6 深度/ depth 孔壁铅垂度/ verticality for holes 安装前,复查基础尺寸和机组实物尺寸相一致。将基础二次灌浆层的表面铲成麻面,麻点深度不小于10mm,每平方分米3~5点,同时将放置垫铁处的基础铲平。
Before installation, physical review basic dimensions and unit size consistent. Based second grouting layer on the surface of the shovel into pits, pit depth shall not be less than 10mm, per square decimeter of 3 ~ 5, also will be placed pad iron base leveled.
(4)泵的安装 (4).Pump installation
a, 泵类设备采用有垫铁法安装。电机驱动的泵以泵体为基准进行找平、找正。联轴器的对中采用双表法。
A. Pump apparatus using a mounting pad. Motor driven pump to the pump body as a benchmark for leveling, find it. Coupling alignment should be done through double meter method. b, 施工现场具备条件后,查明泵的安装方位和标高,进行泵的安装。 B.Construction site with the conditions, to identify the installation position and elevation of the pump, the installation of the pump.
19
轴轴轴向表表架陕西建工安装集团有限公司 SCEGC Installation Group Co., Ltd
c, 在基础上放置临时垫铁组,将泵吊装就位。
C. The pump will be hoisted into placeon the basis of the placement of temporary pad iron group.
d, 一次灌浆达到强度的75%后,调整垫铁,进行泵的二次找正、找平。合格后,拧紧地脚螺栓,监视泵的水平,不应有变化。点焊垫铁组。
D.One time grouting reaches the strength of 75%, adjusting pad iron, pump secondary is leveling. After passing, tighten the anchor bolts, monitoring the pump level, should not change. Spot welding iron pad group.
垫铁安放时应在每个地脚螺栓的旁边至少有一组垫铁;应放在靠近地脚螺栓和底座主要受力部位下面;相邻两垫铁组间的距离,宜为500—1000mm;每组垫铁的面积,应符合下式的要求:A≥C100(Q1+Q2)/nR
其中A是每组垫铁的面积(mm2);
Q1是设备等加在垫铁组上的载荷(N);
Q2是地脚螺栓拧紧时在垫铁组上产生的载荷(N); R基础或地坪混凝土的抗压强度(Mpa).可取混凝土设计强度; n是垫铁组的组数;
C是安全系数,宜取1.5—3;
每一垫铁组 块数不宜超5块,并使用一对斜垫铁。平垫铁的厚度不宜小于2mm;放置平垫铁时,厚度宜放在下面,薄的放在中间。
设备调平后平垫铁宜露出10—30mm, 斜垫铁宜露出10—50mm,垫铁组伸入设备底座的长度应超过地脚螺栓的中心。
e, 根据技术文件的要求,对于国产的小型机泵应进行解体清洗、检查、测量,测量口环间隙、轴承间隙、转子串量及半串量,并作好记录。
E.Domestic mini pump should be disintegration of cleaning, inspection, measuring in accordance with the requirements of technical documents, and metering orifice ring gap, bearing clearance, the rotor on and on volume and prepare records.
f, 联轴器对中应在泵解体检查后进行,并应按照规范要求进行找正,保证机泵的长期安全运转。
F.Coupling should be in the pump after the disintegration of the inspection, and should be in accordance with the requirements of the specification, to ensure the long-term safe