77范文网 - 专业文章范例文档资料分享平台

主机滑油串油工艺中文版1[1](2)

来源:网络收集 时间:2020-05-18 下载这篇文档 手机版
说明:文章内容仅供预览,部分内容可能不全,需要完整文档或者需要复制内容,请下载word后使用。下载word有问题请添加微信号:或QQ: 处理(尽可能给您提供完整文档),感谢您的支持与谅解。点击这里给我发消息

2.1 All out-of-engine pipes of M/E L.O. system to be taken off for acid pickling and cleaning. The installation completeness of pipes of M/E L.O. system to be accepted by QC and Owner.

2.2 The equipments, line and parts on line must be cleaned inner before installation, the gasket installation to be correct and pay more attention to the following: A. two L.O. pumps

B. outlet valves of the two L.O. pumps

C. heat coils and supports in M/E L.O. SUMB TANK

D. venting pipe and return pipes in M/E L.O. SUMB TANK

2.3 The cleaning of the M/E inner, the general L.O. pipe on M/E and the M/E L.O. SUMB TANK to be accepted by Q.C and OW. Before grinding the M/E L.O. SUMB TANK, every pipe hole inside to be sealed with stoppers and take them off before inspection (Q.C check)

2.4 To reduce the flushing period, purifiers to be used during flushing. A temporary filter to be fitted on the line from

purifiers to M/E L.O. SUMB TANK and check the filter in interval . 2.5 Spraying oil to M/E inner 、 parts inside and chain box etc. should be carried out before external flushing or at the beginning of external flushing. 【note : the bearings(main bearing、crosshead、thrust bearing etc. ) to be covered with

canvas. if necessary ,spraying oil to M/E inner to be done again to removing the dirt from flushing before the inspection of external flushing.】To avoid the dirt going into the M/E L.O. SUMB TANK, a filter with mesh 80u to be fitted on the outlet of M/E before spraying oil and accepted by Q.C. (keep the temperature 60-65°c)

2.6 Disconnected the L.O. pipe connected to M/E and covered with blank flange. At position A as shown in attached fig.1 a filter with mesh 25 ? to be fitted, a hose from A to be led to the bottom of the M/E through the temporary side cover.

2.7 Flushing filter with mesh 80 ? supplied by shipyard to be fitted in the main by-pass filter (at position B shown in

attached fig.1). At the beginning of flushing the M/E L.O. Cooler and M/E L.O. Automatic filter don’t join in flushing, when the oil is relatively clean, let the oil go through them.

2.8 Magnets to be installed in the filters at Pos. A, B to absorb iron particles.

6

2.9 Take out of the strainer of L.O. Automatic filter.

2.10 Close the valves on the inlet and outlet of L.O. Cooler and adjust the temperature regulating valve to by-pass position to prevent the dirt hiding in some place (Advice is blanking off the inlet of M/E L.O. Cooler and the side of the temperature

regulating valve connected to the outlet of the M/E L.O. Cooler. If not, drain out the oil in these pipes before opening the

valves on inlet and outlet of M/E L.O. Cooler). Install temporary thermometers on the system.

2.11 Filling 5T L.O. into M/E L.O. SUMB TANK. The level of L.O. in M/E L.O. SUMB TANK to be preferably 300~350mm after starting pumps.

2.12 Check the line again according to the attached fig.1、3.

2.13 Records to be taken both before and during flushing, including spraying and pipe towards.

3. External flushing

3.1 At the beginning of flushing, the two pumps to be used

alternately and pay more attentions to the pressure at inlet and outlet of pump, the voltage and current of motor. If any problems take place, please deal with in time.

3.2 During flushing, take out of the strainers at A、B. After

running the two L.O. pumps at the same time for 24H, put back the strainers and clean the bottom of M/E and take out of the

strainer at outlet of M/E to continue flushing. L.O. purifiers to be in service during flushing to transfer the system L.O. to the M/E L.O. SUMB TANK and to circulating it to clean flushing oil. 3.3 A temporary filter to be fitted to the general pipe of the outlet of L.O. pump to prevent the dirt from M/E L.O. SUMB TANK into line. Check and clean the filter when the main L.O. Pump is running about 10 minutes first time. When the filter became more and more clean, increase the space-time. When the oil is relatively clean, dismantle the temporary filters.

3.4 The flushing oil to be heated to 60oC ~65oC. Temperature at main L.O. cooler preferably to 70oC.

3.5 The pipes to be vibrated continuously with vibrator during flushing. Manual hammering to be performed at flanges and pipe bends and welding parts at regular intervals.

7

3.6 Inlet and outlet valves for L.O. by-pass filter and Automatic filter to be so adjusted that L.O. flush through the filters alternately.

3.7 When QC and technologist agree that the oil is relatively clean, the filter inserts in Pos. A and B to be changed with mesh 25u. Two L.O. pumps to be run simultaneously to continue flushing and after 24 h a sample to be taken for particle counting as a reference for the future flushing, and record for QC.

3.8 When the oil is relatively clean, 1) let the oil go through L.O. Cooler, 2) put back the filter insert of Automatic filter and the Automatic filter is to be run for a 24 hour period, with a cleaning cycle of 20 min.

3.9 During flushing check 、clean and change the filters at position A、B at regular intervals.

4. Inspection of external flushing

4.1 Check bags 10? to be fitted in filters at Pos. A, A new filter

with mesh 25? to be fitted in filter at Pos. B.

4.2 One or two pumps are run, depending on the backpressure from the

check bags, for 2 hours.

4.3 A sample is drawn from the top cover of the Check bag filter

housing.

4.4 If no hard particles in the check bags and particle counting of

the of the oil sample is within limits , then the flushing of internal piping can be prepared.

4.5 Owner to be submit sample record (the particle counting record

to be attached)and flushing record.

5 Internal flushing

5.1 As shown in Fig. 2 and Fig.3, crosshead bearing inlet and main

bearing L.O. inlet to be fitted blank flanges with draining pipes respectively. The flange at in-engine oil inlet of crosshead flexible pipe to be loosen about 5mm to remove entrapped oil.(this item must be finished before external flushing.)

5.2 Install filter 25u at Pos.B to run two L.O. pumps to flushing, 5.3 When technologist agrees that the oil is relatively clean,

dismantle blank flange of chain box spray pipe. The plastic

8

hoses from nozzle to be lead to the bottom of the M/E. (Some nozzles couldn’t be connected to plastic hoses).

5.4 Circulating for 6 hours to the general L.O. pipe on M/E. Record

and inspected by QC.

5.5 All filter elements to be drawn. Two L.O. pumps to be run

simultaneously for 24h. Sample to be drawn for inspection and then submit to Owner.

6 Inspection of internal flushing

6.1 Housings of check bags of 10 ? to be fitted respectively at the

ends of L.O. main of main bearing and crosshead L.O. main. Sample to be drawn for inspection while owner present. 6.1 Continue in accord with 4.2、4.4、4.5.

7 After flushing completion

7.1 Dismantle the blind flanges and hoses and check bags, connect

back the pipes in M/E. and put back the original filter of L.O. by-pass filter at pos. c.

7.2 The oil in the M/E L.O. SUMB TANK to be transferred to the L.O.

settling tank through the L.O. purifier and then be circulated in L.O. settling tank

7.3 The M/E L.O. SUMB TANK to be cleaned and inspected for QC and

Owner.

7.4 If necessary, clean the end of general pipe by dismantling the

blind flange

8 Inspection after flushing completion

8.1 The oil in the L.O. setting tank to be transferred to the M/E

L.O. SUMB TANK through the L.O. purifier and then be circulated in M/E L.O. SUMB TANK

8.2 Restore all piping to normal running condition. Inspected by QC

and OW before running M/E.

9

艉管滑油系统串油工艺

1. 下水前串油

1) 清洁艉管滑油重力油柜和艉管滑油柜,报QC和OW确认; 2) 在附图4所示的位置连接好串油泵和串油滤器(100μ); 3) 在艉管滑油循环柜中加入适量串油用油(同艉管滑油系统油); 4) 按附图4实线所示连接好临时管,启动串油泵,在串油过程中开闭相关阀

件,使串油滑油流经图中实线所示的所有管路及附件并循环直至串油滤器清洁,报QC和OW确认后,串油结束;

5) 最后将串油后的滑油驳至滑油重力油柜用于下水。

2. 下水后串油

1) 当附图中虚线所示管路完整后,将其全部拆回车间以便在车间串油; 2) 车间串油与下水前串油的泵和滤器相同; 3) 当串油滤器清洁时,报QC和OW确认;

10

百度搜索“77cn”或“免费范文网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,免费范文网,提供经典小说教育文库主机滑油串油工艺中文版1[1](2)在线全文阅读。

主机滑油串油工艺中文版1[1](2).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印 下载失败或者文档不完整,请联系客服人员解决!
本文链接:https://www.77cn.com.cn/wenku/jiaoyu/1052731.html(转载请注明文章来源)
Copyright © 2008-2022 免费范文网 版权所有
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ: 邮箱:tiandhx2@hotmail.com
苏ICP备16052595号-18
× 注册会员免费下载(下载后可以自由复制和排版)
注册会员下载
全站内容免费自由复制
注册会员下载
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: