D.处理实际监理事务中,要有大局观,要全面地分析和思考

● 以下做法正确的是(70) 。

A.承建单位要求项目暂停实施,总监理工程师签发“停工令”

B.由于出现项目质量问题,必须进行停工处理,总监理工程师签发“停工令” C.发生必须暂停实施的紧急事件,总监理工程师代表签发“停工令”

D.发生需要停工事件,但建设方暂不允许项目暂停,总监理工程师不签发“停工令”

● 10BaseT is an Ethernet LAN term meaning a maximum transfer rate of 10Mbps that uses baseband signaling and twisted

pair cabling. A 10BaseT Ethernet LAN has a (71) topology. A.star B.ring C.bus

D.none of the above

● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that

helps organize and define the total work scope of the project. A WBS is most useful for(72) . A.identifying individual tasks for a project B.scheduling the start of tasks C.scheduling the end of tasks D.determining potential delays

● Sub-contractors should obey the contractor in information system project. When censoring sub-contractors, the

supervisor mostly concerns about (73). A.Amount of subcontract

B.qualifications and abilities of sub-contractors

C.responsibilities and obligations of sub-contractors D.the contents of the subcontract

● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of

today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According

to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) . A.Ahead of schedule B.Behind schedule C.On schedule

D.Having not enough information provided

● Which statement about the preliminary design stage of a software development project is true? (75) .

A.The preliminary design is an internal document used only by programmers

B.The preliminary design is the result of mapping product requirements info software and hardware functions

C.The preliminary design of the product comes from the requirement specification

D.The developers produce the preliminary design by defining the software structure in enough detail to permit coding

答案:

1-10 BAABB BACDD 11-20 DAADB BCACD 21-30 ABACD CBDBB 31-40 BCBCD CBADC 41-50 BBABC BADBC 51-60 ACCCB ADABB 61-70 ADDCA DBDCB 71-75 AABBC

百度搜索“77cn”或“免费范文网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,免费范文网,提供经典小说综合文库2011上半年信息系统监理师试题(上午)及答案(3)在线全文阅读。

2011上半年信息系统监理师试题(上午)及答案(3).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印 下载失败或者文档不完整,请联系客服人员解决!
本文链接:https://www.77cn.com.cn/wenku/zonghe/312923.html(转载请注明文章来源)
Copyright © 2008-2022 免费范文网 版权所有
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ: 邮箱:tiandhx2@hotmail.com
苏ICP备16052595号-18
× 注册会员免费下载(下载后可以自由复制和排版)
注册会员下载
全站内容免费自由复制
注册会员下载
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: